Building licensing decision

Legislative and regulatory references

- Law No. 122 of 1994 dated on November 28, 1994 relating to the edition of Land Initialization and Reconstruction Journal, as it was completed and revised by subsequent texts

Decision of the Minister of Equipment, Housing and Territorial Development issued on April 17, 2007, regarding the seizure of the documents constituting the building permit file, its validity and extension, and the conditions for its renewal (Chapter Two)

Decision of the Minister of Equipment, Housing and Territorial Development, on April 17, 2007, regarding the regulation of the installation and methods of functioning of the technical committees for building permits

Conditions for having service

 That the requester obtain a building permit, the subject of the extension request

Do not make any changes to the building subject to the license, otherwise a new building permit is required

The request for extension must reach the municipality one month before the date of the expiry of the building permit subject to the request for extension

The required documents

An application on behalf of the mayor, on a regular paper signed by the person concerned

Filing placement

- Technical service in the Municipality or the municipal department

Placement of having service

- Technical service in the Municipality or the municipal department

Time limits

- Within 21 days from the date of submitting the complete file   

- Within 60 days if the building is in an area whose initialization is in progress.

- Within 90 days, as the building is about 200 meters of natural, cultural, archeological, preserved, or historical locations.